Contractor appointed to prepare London Overground network for longer trains
Longer trains to provide a
25 per cent increase in capacity by end of 2015
- Contractor will extend or modify station platforms on the Clapham
Junction/Richmond to Stratford London Overground routes
Transport for London (TfL) today appointed leading construction and civil
engineering firm Dyer and Butler as the contractor to lengthen and modify some of the
station platforms on the Clapham Junction/Richmond to Stratford London
Overground route.
The work is part of a huge upgrade
programme to deliver an additional 25 per cent capacity to meet increasing
demand on the capital’s fastest growing railway.
Since TfL took over the network in 2007,
London Overground has become one of the UK’s most reliable rail services and passenger numbers have
quadrupled - from 2.5m in a typical 4 week period in 2008 to 11.2m.
The longer platforms will
accommodate longer London Overground trains, which are being increased from
four to five carriages. The first of these longer trains will run on the
Highbury & Islington to New Cross/Crystal Palace/West Croydon/Clapham Junction
routes from the end of 2014, followed by the Clapham Junction/Richmond to Stratford routes
by the end of 2015.
The work is part of the £320m London
Overground Capacity Improvement Programme (LOCIP), which continues TfL’s
investment in this highly successful railway. TfL has already delivered more
frequent and punctual services, a new fleet of air-conditioned, high capacity
trains and most recently the completion of the London Overground orbital
network around London – the first orbital rail network in the capital for 128
years.
TfL’s Director of London Overground,
Mike Stubbs, said: “Although still in its infancy, London Overground services
have proved to be hugely popular with passengers, with numbers quadrupling
during the first six years of service. As London’s population continues to
grow, so too will the demand on London Overground, which is why we’re carrying
out vital work such as this to help provide the extra capacity that will be
needed. We’re really pleased to be working with Dyer and Butler on this
crucial project and will work closely with them to ensure the minimum of
disruption to services.”
TfL will take over routes that run
from Liverpool Street station to Enfield Town, Cheshunt (via Seven Sisters) and Chingford, which include 25
stations in total across six London Boroughs. This follows work by the Mayor
and TfL to set out the benefits of devolution as demonstrated by the London
Overground model.
Work at the first London Overground
stations on the Clapham Junction/Richmond to Stratford route
is expected to begin in February 2014 while work on the Highbury &
Islington to New Cross/Crystal Palace/West Croydon/Clapham Junction routes will
begin later this month.
·
Extensions or the refurbishment of disused
platform space will be required at the following stations on the Richmond/Clapham
Junction to Stratford route:
-
South Acton
-
Acton Central
-
Willesden Junction High Level/Low level
-
Kensal Rise
-
Brondesbury Park
-
Brondesbury
-
West Hampstead
-
Finchley Road and Frognal
-
Hampstead Heath
-
Gospel Oak
-
Kentish Town West
-
Camden Road
-
Caledonian Road and Barnesbury
-
Dalston Kingsland
-
Homerton
-
Canonbury
-
Highbury & Islington
All train images provided courtesy of Haydn Davies
·
The platform extensions on the Highbury
& Islington to New Cross/Crystal Palace/West Croydon/Clapham Junction
routes are being carried out under a separate contract with Cleshar Contract
Services
·
With the exception of the works starting in
late December, the exact timing and duration of works at each station is still
being finalised. However they are likely to be scheduled during the following
phases.
December 2013 – March 2014
|
Highbury & Islington and Canonbury (East London
Line platforms), Surrey Quays
|
February – April 2014
|
Dalston Junction, Hoxton and Haggerston
|
February– July 2014
|
South Acton,
Acton
Central, Willesden Junction and Wandsworth
Road
|
April – June 2014
|
Shoreditch High Street, Shadwell,
Canada
Water, Clapham Junction and Wapping
|
May– November 2014
|
Kensal Rise, Brondesbury Park,
Brondesbury, West Hampstead, Finchley Road & Frognal, Hampstead Heath,
Gospel Oak, Kentish Town West
|
September 2014 – April 2015
|
Camden Road, Caledonian Road &
Barnsbury, Highbury & Islington (North
London Line platforms), Canonbury (North
London Line platforms), Dalston Kingsland, Homerton
|
·
As well as the platform lengthening, other
works included in the London Overground Capacity Improvement Programme include:
-
Construction of a new stabling facility at
Silwood in south-east London
-
Additional stabling in the north-west London area
-
Reconfiguration of the New Cross Gate and
Willesden train maintenance depots
-
Signalling and power works associated with
the platform extensions and depot/stabling modifications
·
Platforms on the Clapham Junction to
Willesden Junction route will be extended by Network Rail under their 8-car
works for Southern Trains by March 2014.
·
At stations where platform extension is not
a viable option to accommodate the longer trains, we will introduce selective
door operating which will be facilitated by the open walk-through design of the
carriages. This will be required at Whitechapel (temporarily until Crossrail
completes construction), Wapping, Rotherhithe and Canada Water as it is not
possible to extend the platforms to the required length without completely
rebuilding the stations. Train announcements will provide advance warning about
which doors will not open once the longer trains are introduced.
·
*The Government’s commitment to electrify
the Gospel Oak to Barking line will also allow for the introduction of higher
capacity trains on this route at a later date.