Deteriorating’ Cambridgeshire guided busway may need to be ripped up
The busway, which runs between Cambridge and Huntingdon, has had
11 million passengers since it opened four years ago, but it has been
plagued with defects.
A technical report six months ago said the
busway, which was built by contractor BAM Nuttall, had £31 million worth
of defects - in some places the track has risen four inches - which
need to be addressed to tackle the “deteriorating” ride quality.
Next weekend, the section from Addenbrookes’s Hospital to Trumpington will be shut for maintenance.
Speaking to BBC Radio Cambridgeshire, Bob Menzies, service director for strategy and development at Cambridgeshire County Council, said they may be forced to put rubber pads under every beam of the track.
Speaking to BBC Radio Cambridgeshire, Bob Menzies, service director for strategy and development at Cambridgeshire County Council, said they may be forced to put rubber pads under every beam of the track.
“The ride
quality has deteriorated since it opened, and the joints are moving.
The last thing we want to do is to have to do this work. But on the
other hand we have to make sure it’s maintained and kept safe,” he said.
“It’s
a real shame we have this problem, that we’re having to close it over a
weekend, having to divert the buses round, and we many have to do more
of this in the future.
“Our experts’ view is that eventually we’ll need to fix it all. And it’s a real shame.
“If
we (the county council) have to we’ll lift every beam up and put these
rubber pads back under each one of them as they should have been done
properly in the first place.”
Replacing beams cost several thousand pounds at a time, so replacing 6 million joints could add up to a “very big figure”, Mr Menzies admitted.
Replacing beams cost several thousand pounds at a time, so replacing 6 million joints could add up to a “very big figure”, Mr Menzies admitted.
The council has already
spent £1 million on legal action against Bam Nuttall in a bid to get
them to take responsibility over the repairs, Mr Menzies added.
He
said: “What we believe should happen is Bam Nuttall should come back
and fix it all, and get the ride quality back to where it should have
been.
“They’re quite clearly defects. It quite clearly doesn’t
comply with the terms of the contract. I’m absolutely clear about that,
and so are our lawyers. There’s six thousand joints along the busway -
that could add up to a very big figure if you have to fix every one over
the course of a number of years. That’s why we’re taking legal action
against Bam Nuttall.
“I’d like Bam Nuttall to come clean and
accept their responsibilities. But I suspect it won’t. In effect it will
take a lot longer than that, knowing the previous history.”
The
initial contract between Cambridgeshire County Council and BAM Nuttall
was for 130 weeks of work, with the completion date on February 27th,
2009.
But the busway construction was not completed until April
2011 and not open for use until August of that year as the council
raised concerns about defects along the guideway.
The council
instigated the review into the contract after the project ran into
problems and delays, resulting in BAM Nuttall, repaying £33million of
the £147m costs to settle a long-running dispute about who should pay
for the overspend for the concrete route.
The report found BAM Nuttall did not think the design was as complete as it expected it to be when the contract was awarded.
Involving
a consultant to review the design was not value for money and removed
responsibility from the contractor’s designer, the report added.